Zeus Mitchell Campus
Enterprise-Scale AI Training Data Center | Texas
Project Overview
Zeus Mitchell Campus is a hyperscale data center complex specifically designed for AI training workloads, featuring enterprise-grade infrastructure and sustainable power solutions in Texas.
Total Capacity: 2.1 GWac Data Center Complex
Configuration: 14 powered shells @ 150MWac each
Site Size: 300 acres (with 6,000+ acres available for expansion)
Shell Footprint: 20 acres per shell
First Phase Online: 100+MW by Q2 2027
Power Infrastructure
Grid Connection & Utility
Utility Provider: Oncor (Transmission Service Provider & Load Serving Entity)
Grid: ERCOT (Electric Reliability Council of Texas)
Transmission: Primary power provided via 345kV Oncor T-line to support 2,100MW DC point of interconnection
Redundancy: Three breaker ring bus configuration at 345kV
Grid Fuel Mix: 48% natural gas, 16% solar, 16% wind, 12% coal, 7.5% nuclear
On-Site Power Generation
Solar Generation: 800MW utility scale solar project
Battery Storage: 1,000MW battery energy storage system (BESS)
Future Expansion: Additional 1,500MW CCGT natural gas plant capability
Power Integration: Direct behind-the-meter interconnection of solar and BESS to data center
Site & Infrastructure
Location Advantages
Transportation: Major Texas interstate highway adjacent to site
Expansion Ready: 6,000+ acres under site control – an additional 1,000 acres available for future expansion if needed
Environmental: Environmental Critical Issue Analysis (ECIA) complete (July 2023) and Phase I ESA studies complete (Dec 2024) - No environmental areas of concern or protected wetlands identified (Feb 2025)
Land Holdings
Multiple contiguous parcels totaling 6,000+ acres under lease
LOIs to purchase 500-600 acres for DC specific use in negotiations on land already under lease control by Zeus
Largest parcels: 640 acres (multiple), 620 acres, 480 acres, 460 acres
Strategic parcel positioning for optimal campus development
Connectivity
Primary Provider: AT&T
Network Access: Multiple Central Offices within 80km
Metro Connectivity: Direct links to DASH (Dallas, Austin, San Antonio, Houston)
Development Status & Timeline
Current Phase
Site control secured with 19 parcels under lease
Preliminary geotechnical analysis completed
ECIA, Phase I ESA, and wetlands delineation study finalized (Aug 2024/Feb 2025)
Utility interconnection studies for load and generation underway with ERCOT/Oncor
Established strategic partnerships with solar and BESS OEM suppliers and BoP EPC
Next Milestones
30-60% design phase for precise micro-siting
ALTA survey work for final acreage confirmation
Geotechnical studies for foundation design (completed on adjacent site. No issues expected)
Transportation impact study with EPC contractor
Reservation Payments to secure manufacturing slots for long lead-time items (MPTs, etc)
TAA 312 agreement with Mitchell County
Delivery Timeline
Q2 2027: First 100+MW shell online
Phased Delivery: Consecutive construction of additional shells based on tenant requirements
Sustainability & ESG
Renewable Energy Integration
On-site Solar: 800MW capacity directly serving data center
Battery Storage: 1,000MW BESS for grid stability and renewable integration
Grid Mix: 32% renewable sources (16% solar + 16% wind) from ERCOT
Future Flexibility: Natural gas backup capability for reliability
Environmental Compliance
No significant wetlands impact
Stormwater management and prevention planning included
Rural location minimizes urban infrastructure strain
Permitting Advantages
Rural Location: No municipal permits, zoning restrictions, or height limitations required
Streamlined Process: No county or city approvals needed for construction
Regulatory Relationships: Direct communication established with TCEQ Deputy Director
Utility Support: Executive buy-in from Oncor for substation permitting
Experience: Extensive knowledge of local permitting through previous natural gas project development in Mitchell county
Labor & Workforce Availability
Construction Workforce
Regional Availability: No known constraints for construction labor in the region
Cost Structure: Accommodates rural conditions with competitive regional rates
Labor Relations: Right to Work Non-unionized workforce with no history of labor disputes
Contractor Relationships: Existing relationships with local contractors established
Commissioning: Qualified commissioning workforce available
General Contractors: Final negotiations in progress with experienced EPC partners
Specialized Technical Workforce
Electrical Specialists
Regional Supply: Ample qualified electricians with proximity to major Texas markets
Scalability: Workforce can scale according to project timeline with staggered implementation
High-Voltage Expertise: Local high-voltage specialists available
Data Center Experience: Access to contractors with proven data center experience
Certifications: Teams working on NEC compliance and critical certifications
Key Partners: EPE, Mortenson & Worldwide Mission Critical contributing expertise
Mechanical & Plumbing Resources
HVAC Systems: Experienced mechanics available for facility piping and cooling systems
Advanced Cooling: Architect experience with direct-to-chip liquid cooling arrays
Regional Partners: Multiple OEM partners in Dallas/Fort Worth area for installation support
Timeline Impact: Mechanical workforce not expected to limit overall project timeline
Vendor Network: Established relationships with regional plumbing and mechanical contractors
Connectivity & IT Infrastructure
Fiber Infrastructure: Establishing strategic partnership with AT&T
Redundancy: Minimum of three ingress points for redundant fiber connectivity
Installation: Connectivity labor availability will not limit build timeline
Deployment Speed: Service capabilities designed for rapid deployment when needed
Resources & Supply Chain
Material Availability & Logistics
Heavy Machinery: Multiple regional suppliers with no sourcing concerns
Commodities: No lead time differences for concrete, steel, and standard materials
Year-Round Access: All-weather site access with no seasonal build restrictions
Working Hours: No local constraints on construction hours or times
Environmental Approvals: No anticipated restrictions on build hours
Equipment & Storage Solutions
On-Site Capabilities
Warehousing: Suitable regional warehousing available; on-site staging areas prepared
Equipment Storage: Secure perimeter and storage for materials and equipment
Weather Protection: Weatherization protection for early-arriving specialized equipment
Material Security: Total control measures for all on-site assets
Critical Equipment Timeline
Major Power Transformers (MPTs): 16-18 month lead times
Circuit Breakers: 16-18 month lead times
Solar & BESS: Just-in-time delivery and installation (Texas standard practice)
Delivery Coordination: Single delivery scheduling for proper ingress/egress monitoring
Supply Chain Advantages
Regional Sourcing: Access to Dallas/Fort Worth industrial corridor
Multiple Suppliers: Diversified supplier base reduces risk
EPC Confirmation: Lead times and availability confirmed by multiple EPC contractors
No Bottlenecks: Working with EPC teams to ensure no workforce bottlenecks
Key Competitive Advantages
Scale & Flexibility
Hyperscale capacity with modular deployment options
2-story or 3-story shell configurations available
Massive land availability for tenant-specific requirements
Power Reliability
Rural power distribution demonstrably more reliable than urban
Multiple power sources: grid, solar, battery, future gas
No extraordinary vulnerabilities predicted for power access
Infrastructure Readiness
Suitable foundation conditions across campus footprint
Multiple suitable access roads for construction and operations
Ample space for parking and construction staging
Strategic Location
Texas business-friendly regulatory environment
ERCOT grid participation with competitive power markets
Proximity to major Texas metros via interstate access
Tax Abatement Agreements (TAA) and Value Limitation Agreements (VLA)
Solar/BESS have TAAs in place with county, DC will negotiate and enter into a TAA in the next 4-6 months (Texas Tax Code Section 312)
Solar/BESS have in place executed VLA – VLA program no longer available (Texas Tax Code Section 313)
Additional 1,500MW CCGT site sits on directly adjacent land that is already owned outright, and has legacy SGIA, Air Permit, Geo-tech, 312 tax abatements, etc.
Technical Specifications
Power Configuration
345kV grid connection with Oncor ownership of high-side substation
Low-side substation wholly owned by Zeus/tenant
Three breaker ring bus configuration for maximum reliability
Site Preparation
Buildability assessment completed
No significant geotechnical concerns identified
Flexible design accommodation for tenant requirements
Operational Support
DCIM management options available based on final design
Local warehousing capabilities for equipment staging
EPC contractor coordination for construction logistics
Contact Information
For detailed specifications, site visits, or lease discussions, please contact the Zeus development team. Trey Berndt; trey@zeusred.com
This fact sheet is based on the official Zeus Mitchell Campus RFI documentation dated May 1, 2025.
Data Center
Fiber